EME 09 Risk management

发布时间 2023-04-03 09:10:27作者: xwx123

Risk management

  • Identify the risks that might affect the project’s success.
  • Assess the risks based on cost-effective principal.
  • Select appropriate methods to mitigate project’s risks.
  • Estimate risks to the schedule using PERT & Critical
    Chain technique

Risk

involves “cause vs effects”.
The key role of risk management is considering uncertainty remaining after a plan has been formulated.

Risk Management Process

compare loss & the cost of defraying

  • risk identification
  • risk assessment
  • risk plan
  • risk monitoring & control

Risk Identification

  • Technical risks
  • Project management risks
  • Organizational risks
  • External risks

Risk Identification Matrix Template

scope triangle elements:

  • scope
  • time
  • cost
  • quality
  • resources

Risk Assessment

risk exposure = (potential damage) × (probability of occurrence)
e.g. 500k*0.1%=500 yuan
level: high>significant>moderate>low

Risk Plan

  • risk accept
  • risk avoidance
  • risk reduction/mitigation
  • transfer